Updates / October 08, 2019
To assist us in the detailed design of the scheme, a Ground Investigation Survey in the Whitechurch Road area will commence on 14/10/2019, with the surveys scheduled to last 3 weeks.
The Ground Investigation Survey consists of taking soil samples and determining the location of underground services by the use of Boreholes, Trial Pits and Slit Trenches. As most of the works will be carried out on public footpaths and roads, pedestrian and traffic management will be put in place to accommodate the works so we ask road and footpath users to follow all site signage and thank you in advance for your patience while the works are on-going.
As work locations are agreed over the coming days, further information will be placed on this website highlighting the areas that will be affected on a given day.
If you have any queries please contact David Grant, Project Resident Engineer at 086-0211451 or by using the project email address on the contact page info@whitechurchfas.ie
15/10/2019; Work Locations for w/e 18/10
16-17/10: BH13 – Willbrook Grove Footbridge
17-18/10: BH12 – Grassed area below entrance to Willbrook Lawn
21/10/2019; Work Locations for w/e 25/10
21-22/10: BH11 – Grass Area East of entrance to Willbrook Cul de Sac
22-23/10: BH10 – Grass Area West of entrance to Willbrook Cul de Sac
24-25/10: BH09 – Private Property